Edinburgh march demands a local say on AI data centres
Thousands marched to the Scottish Parliament in Edinburgh against large AI data centres, bringing community concerns about energy, construction and local decision making into the streets. Campaigners sought a stronger voice in approvals and a pause on large projects. Scotland’s government defended the planning system and said new guidance would be published before the end of the year.
Artificial Intelligence··Midday
Community groups march to parliament
Thousands of demonstrators walked through Edinburgh on November 14 to oppose large AI data centres and demand a say in approvals. The route took them along the Royal Mile to the Scottish Parliament. STV News put attendance at an estimated 6,000. Community campaigns against projects in Cockenzie and Larbert joined the march, alongside groups from other parts of Scotland. Some participants wore costumes to draw attention to their concerns.[1], [2]
Campaigners raised concerns about energy bills, environmental effects and how local residents were represented in decisions. The Scottish Greens and campaign groups called for a pause on large centres. Kim Pratt of Friends of the Earth Scotland said residents should be heard in decisions affecting their communities, linking the campaign to concerns about climate effects and resource use.[1], [2]
Proposals seek large grid connections
September figures from electricity system operator NESO, cited by STV, showed 28 proposed Scottish data centres waiting for grid connections totalling 8.9 gigawatts. That requested capacity exceeds twice Scotland’s current winter peak electricity demand. It describes proposals awaiting connections, rather than electricity already being consumed by operating centres. The existing DataVita facility at Airdrie, in North Lanarkshire, was described as Scotland’s largest at 12 megawatts.[1]
For Chapelcross in Dumfries and Galloway, the proposed centre would reach 1,000 megawatts if built. Local campaigner Kim Cairns told the BBC that construction could bring noise, closed roads and access problems. She also voiced concern about noise once the centre was operating and the replacement of green fields. DataVita managing director Danny Quinn argued that regional AI computing capacity was needed to avoid dependence on overseas providers.[2], [1]
Government promises planning guidance
Innovation minister Alyn Smith defended Scotland’s planning system. The government said new guidance would be issued before the year ended and a strategy was being developed to maximise public benefit. Planning authorities must notify ministers about new data centre applications. The government also reiterated that new facilities above 50 megawatts need an environmental impact assessment, as campaigners sought greater participation in shaping the rules.[1], [2]