Assam’s Sonitpur solar farm starts selling electricity
The Sonitpur solar project in India’s northeastern state of Assam has brought 45 megawatts into commercial operation out of a planned 50 megawatts. The state’s power distributor issued a trial run certificate and is buying the electricity under an existing contract. A subsidiary of Indian electricity producer SJVN developed the project.
Economics & Markets··Midday
The first capacity enters commercial operation
India’s electricity producer SJVN told stock exchanges that its subsidiary SJVN Green Energy had put 45 megawatts of the Sonitpur solar project into commercial operation on 21 November. The project is in Assam, in northeastern India. The state’s electricity distributor approved the trial run that day and is buying power under a previously signed agreement.[1], [2]
A purchase agreement covers the planned plant
The distributor sought bids in February 2023 for a ground-mounted 50-megawatt solar plant. The developer was to build the facility, own it and run it. The two sides signed the power purchase agreement on 7 February 2024. It covers the full planned capacity. SJVN gave no commercial start date for the last 5 megawatts.[1]
The launch estimate covered the complete site
When the project was launched in March 2024, estimates put its cost at around 2.91 billion rupees and electricity at 3.92 rupees per kilowatt-hour. The planning estimate for the entire plant was about 101 million kilowatt-hours of output in the first year. The exchange announcement marks the start of sales from the portion already in operation at Sonitpur. The new capacity is at Sitalmari village in Barsola. The company announced the commercial milestone to the stock exchanges.[1]